Timber frame extensions

Faster, lighter construction with excellent insulation, finished in cladding, render or brick slips.

  • Guide price£1,750 to £3,400 per m² inc VAT
  • Design and approvals4–12 weeks design and approvals
  • Build time8–14 weeks on site
  • Planning in EnglandOften permitted development (3–4 m), or prior approval up to 6–8 m
Timber frame extension under construction with OSB sheathing and roof joists

A timber frame extension uses a structural frame of engineered or treated softwood instead of brick and block walls. The frame goes up quickly, is lighter on the foundations and makes high insulation levels straightforward.

Externally, timber frame extensions can be clad in timber, render, fibre-cement boards or brick slips, so they do not have to look like timber at all. Internally they are plasterboard-lined like any other room.

What is included

  • Frame design and structural calculations
  • Foundations, often lighter than masonry
  • Breathable wall build-up with insulation
  • Cladding, render or brick slip finish
  • Fire and acoustic details where needed

Who it suits

  • Sites where weight or speed matters
  • Contemporary designs with timber or board cladding
  • Homeowners who want strong energy performance

Design advice

Moisture is the enemy of any timber building. We design ventilated cladding cavities, breather membranes and a proper damp-proof course height, and keep the frame dry during construction.

How much does it cost?

National guide prices including VAT at 20%. Build cost only; design, structural and council fees are extra. Your area page shows prices adjusted for your region.

SizeEssentialStandardPremium
3 m × 4 m
12 m²
£21,000 – £25,500£24,500 – £32,000£31,000 – £41,000
4 m × 5 m
20 m²
£35,000 – £42,000£41,000 – £53,000£52,000 – £68,000
5 m × 6 m
30 m²
£52,500 – £63,000£61,500 – £79,500£78,000 – £102,000

Planning rules across the UK

England

In England a single-storey rear extension can usually go up to 3 m beyond the original rear wall of a semi-detached or terraced house, or 4 m on a detached house, without a planning application, provided it is no more than 4 m high, keeps eaves to 3 m within 2 m of a boundary and, with other buildings, covers no more than half the land around the original house. The larger home extension prior approval scheme raises those depths to 6 m and 8 m, with neighbours notified and a 42-day decision.

Wales

In Wales a single-storey rear extension can usually project up to 4 m beyond the rear wall without a planning application, if it is no more than 4 m high, keeps eaves to 3 m and overall height to 4 m within 2 m of a boundary, and covers no more than half the land around the original house. Wales has no larger home extension prior approval scheme.

Scotland

In Scotland, householder permitted development rules (Class 1A for single-storey ground-floor extensions and Class 1B for extensions of more than one storey) allow some smaller extensions without a planning application, within limits on depth, height and distance from the boundary. Conservation areas and listed buildings are more restricted. Separately, almost every extension needs a building warrant from the council before work starts.

Northern Ireland

In Northern Ireland the Planning (General Permitted Development) Order 2015 lets some single-storey rear extensions go ahead without planning permission, up to 3 m on a semi-detached or terraced house and 4 m on a detached house, within height and boundary limits. Larger, side and two-storey extensions normally need planning permission from the council, and building control approval is separate.

Building regulations and neighbours

Building regulations approval is separate from planning. In England you can use the council's building control team or a registered building control approver; a full plans application gets the drawings checked before work starts, and the inspector signs the work off with a completion certificate.

In England and Wales, if the work involves a shared wall, building on the boundary, or digging foundations within 3 m (sometimes 6 m) of a neighbour's building, the Party Wall etc. Act 1996 applies and notice must be served before work starts: two months for work to a party wall, one month for new walls on the boundary and for excavations. Scotland and Northern Ireland have no Party Wall Act.

Questions about timber frame extensions

Is timber frame cheaper than brick?

It is similar overall. The frame can save time on site, but the cladding choice has a big effect on cost. Our guide range is about £1,750 to £3,400 per m² including VAT.

Does a timber frame extension need planning permission?

The same planning rules apply as for any extension. If the cladding looks different from the house, permitted development’s matching-materials condition may mean an application is needed.

How long does a timber frame last?

A well-designed and properly protected timber frame lasts as long as a masonry building. Detailing and keeping water out are what matter.

Process

How a project runs

  1. Free site visit

    We visit your home, measure up, talk through what you want and check the planning position.

  2. Design and approvals

    We draw the design, agree it with you and handle planning or permitted development checks and building regulations.

  3. Fixed written price

    With the design and specification agreed, you get a fixed written price and a start date.

  4. Build and sign-off

    We build it with one project manager, book the building control inspections and hand over the completion certificate.

Planning a timber frame extension?

Book a free site visit: we measure up, check the planning route and give honest guide figures.

  • Free, no-obligation site visit
  • Planning route checked before you spend on drawings
  • Written price once the design is agreed
  • Building control sign-off at the end

Prefer to talk? Call 0800 088 6341 or .

Book a free site visit

Tell us a little about the project and we will arrange a time.

Please enter a valid UK postcode.
Please choose an option.
Please enter your name.
Please enter a phone number.
Please enter a valid email.

We use your details only to reply to this enquiry and prepare your quote. Privacy notice.

Call usGet a quote